GPI

Plant Manager

Range: Today Yesterday This Week Last Week This Month Last Month
Custom: 2026-05-01 → 2026-05-01
Drag / resize — layout auto-saves
Total Pallets Processed
2,662
Up Time
79.4 %
Total Downtime
7.5 h
pallets/hr/person
61.2

Pallets by Work Center — Dismantlers

Dismantler 1 (no assignment)
540/550
Dismantler 2 (no assignment)
542/550
Dismantler 3 (no assignment)
305/435
Dismantler 4 (no assignment)
536/550
start · 07:00
now · 14:57
Total 1923 / 2085 (92.2%)

Pallets by Work Center — Repairs

Repair 2 (no assignment)
739/750
start · 07:00
now · 14:57
Total 739 / 750 (98.5%)

All Dismantlers — 15-minute progress

At / above goal Below goal Goal 288/hr · 72 per 15 min
40
56
66
64
73
60
78
72
34
81
93
85
92
81
88
46
85
78
72
69
78
64
68
34
72
66
60
50
2
07:00 07:30 08:00 08:30 09:15 09:45 10:15 10:45 11:45 12:15 12:45 13:15 14:00 14:30 15:00

All Repairs — 15-minute progress

At / above goal Below goal Goal 103/hr · 26 per 15 min
27
29
19
27
33
30
30
29
33
42
22
22
26
21
23
19
25
26
26
25
13
26
22
23
27
26
30
22
12
07:00 07:30 08:00 08:30 09:15 09:45 10:15 10:45 11:45 12:15 12:45 13:15 14:00 14:30 15:00
0

All Dismantlers — Daily Progress

Target Pallets
40
96
162
226
299
359
437
509
543
624
717
802
894
975
1,063
1,109
1,194
1,272
1,344
1,413
1,491
1,555
1,623
1,657
1,729
1,795
1,855
1,905
1,907
07:00 07:30 08:00 08:30 09:15 09:45 10:15 10:45 11:45 12:15 12:45 13:15 14:00 14:30 15:00
0

All Repairs — Daily Progress

Target Pallets
27
56
75
102
135
165
195
224
257
299
321
343
369
390
413
432
457
483
509
534
547
573
595
618
645
671
701
723
735
07:00 07:30 08:00 08:30 09:15 09:45 10:15 10:45 11:45 12:15 12:45 13:15 14:00 14:30 15:00

Downtime Report

Dismantler 1 (no assignment)
85m
Dismantler 2 (no assignment)
76m
Dismantler 3 (no assignment)
147m
Dismantler 4 (no assignment)
75m
Repair 2 (no assignment)
65m